What is the difference between testing start date, testing completion date and Due date?

已回覆
0

評論

1 條評論

  • Isabel Messore

    Somu Sri Pavan Sundeep,

    Happy to provide some clarity here:
    • Start date is when a use starts performing the testing
    • Completion date is when the testing was completed
    • Due date is when a user would like the testing to be done
    Additionally, I've discussed with our experts and they do not foresee any impact by removing the due date!