|
Os tipos de arquivos clássicos não estarão mais disponíveis para uso a partir de janeiro de 2021. Você pode fazer a transição de seus arquivos clássicos ou baixar um PDF. Saber mais

Editing tasks dependencies - Starting two tasks simultaneously when the prior one is finalised

Respondida
0

Comentários

1 comentário

  • Isabel Messore

    Great question Victor Fontenele!

    Your desired workflow (Task A → triggers both Task B and Task C simultaneously) is not natively supported with automatic branching logic in Workiva Processes today.

    What Processes currently supports:
    - All at once — all actions start the moment the process is kicked off
    - One at a time — strictly sequential; each action waits for the previous to finish
    - Manual — the process manager manually starts each action in any order they choose
     
    For your use case, I recommend using the Manual trigger — this is the most flexible option:
     
    1. Set the process to Manual start order
    2. When Task A (Prepare) is complete, the process manager manually starts both Task B (Approve) and Task C (Next work) at the same time
    3. For later actions that truly depend on Task B's approval, the process manager waits for Task B to complete before manually triggering those
     
    This isn't fully automated, but it gives you full control over the branching sequence without restructuring everything. One note I'd like to add is that the start order cannot be changed once a process has been started, so make sure to set Manual before running it.
    0

Por favor, entrar para comentar.